|
|
|
|
|
|
Decision Session – Executive Member for Transport
|
19 July 2022 |
Report of the Director of Transport, Environment and Planning |
Active Travel
Summary
1.
This report presents updated
information on the progress of the Active Travel Programme,
including recommendations for decisions relating to individual
projects within the programme.
2.
The Executive Member is asked to
approve the addition of 3 new schemes to the programme following
the news of a partially successful grant funding bid to the
Department for Transport.
3.
An update on the overall programme
timescales and budget is included, with a proposal on how to manage
the available funds.
4.
The report recommends that the
Navigation Road Experimental Traffic Regulation Order is made
permanent, following a trial period and the outcome of a
consultation process.
5.
Feasibility work is presented for
the City Centre Bridges scheme and the report recommends a decision
is made to proceed to consultation, detailed design and
implementation.
6.
An update is provided for the A1237
Active Travel scheme, with the outcome of the feasibility work
indicating that the project as it currently stands is not viable.
The report explores the reasoning behind this outcome and proposes
to reassign the available resources to other projects within the
programme. Further safety-focussed work is proposed to be pursued
through a separate programme.
7.
Similarly, the Heslington to
Wheldrake path scheme has progressed to a later stage of
feasibility, with the outcome strongly suggesting that the
objectives cannot be achieved within the available budget. A
recommendation is made to reassign the available resources to other
projects within the programme and progress the existing feasibility
through the upcoming LCWIP work (Local Cycling and Walking
Infrastructure Plan).
8.
Feasibility work has been completed
for the People Streets at Ostman Road scheme. This report
highlights the key outcomes of this work and makes a recommendation
on the next steps for the scheme.
9.
The Executive Member is asked
to:
1)
Approve the Project Outline for the
‘City Centre Cycle Parking Improvements’ scheme
attached in Annex 1.
Proceed to undertake Feasibility work to understand costs,
timescales, outline designs and consultation feedback to inform a
further decision prior to implementation. (Option 1)
Reason: To provide
clarity on the objectives and scope of the proposed scheme.
2)
Approve the Project Outline for the
‘People Streets at Clifton Green Primary School’ scheme
attached in Annex 2.
Proceed to undertake Feasibility work to understand costs,
timescales, outline designs and consultation feedback to inform a
further decision prior to implementation. (Option 1)
Reason: To provide clarity on the objectives and scope of the
proposed scheme.
3)
Approve the Project Outline for the
‘People Streets at Badger Hill Primary School’ scheme
attached in Annex 3.
Proceed to undertake Feasibility work to understand costs,
timescales, outline designs and consultation feedback to inform a
further decision prior to implementation. (Option 1)
Reason: To provide clarity on the objectives and scope of the
proposed scheme.
4)
Decide to make the Experimental
Traffic Regulation Order relating to Navigation Road cycle scheme
permanent. (Option 3)
Reason: To successfully conclude the Navigation Road trial
scheme.
5)
Confirm that the proposals presented
for the City Centre Bridges scheme align with the approved Project
Outline, and decide to proceed with consultation, detailed design
and implementation. (Option 5)
Reason: To support progress towards implementation of a
solution.
6)
Support the approach to managing the
programme budget laid out in Section 75 of this report. Note the
programme budget summary attached in Annex 5. (Option 6)
Reason: To ensure an appropriate balance is reached between
obtaining value for money and the expeditious delivery of
schemes.
7)
Note the outcome of the feasibility
work for the A1237 bridge scheme and decide to reassign scheme
resources to the wider Active Travel Programme, subject to DfT
support.
Consideration of longer term active travel provision is to be
considered as part of the Outer Ring Road works.
Shorter term options to improve safety are to be explored through
the separate Safety Scheme Review process within the Transport
Capital Programme. (Option 7)
Reason: The scheme has been determined to not be feasible due to
reasons laid out within section 90.
8)
Note the reported position on the
Wheldrake to Heslington scheme and decide to reassign resources to
the wider programme, subject to DfT support.
Progression of existing feasibility work is to be considered as
part of the development of the Local Cycling and Walking
Infrastructure Plan. (Option 9).
Reason: The scheme has been determined to be unaffordable within
current budgets, due to the reasons laid out within section
106.
9)
Note the outcome of the feasibility
work for the ‘People Streets at Ostman Road’ scheme
laid out in section 125 and decide to seek further funding before
proceeding to implementation.
Seek Active Travel grant funding support at the next round of
bidding.
Progress with detailed design work on Design Option 1 presented
within Annex 8. (Option 11)
Reason: Feasibility work indicates that whilst a practically
achievable scheme has been identified, there is currently
insufficient budget to deliver the scheme.
Brief Update on ‘Very High Priority’ Schemes
10.
Refer to Annex 4 for a brief update
on the overall programme. The table includes a column showing the
priority of each scheme. This section gives a brief update on the
progress of those schemes determined to be of ‘Very High
Priority’.
11.
University Road Minor Pedestrian
Works – This scheme is due for construction in August. Final
arrangements are underway.
12.
A19 Cycle Scheme – Outputs
from the feasibility work are due w/c 11th July. This
information will be reviewed and the intention is to undertake
consultation thereafter, timescales dependant upon the specific
content of the feasibility work and its implications.
13.
A1237 Bridge Scheme –
Feasibility work is complete and this report covers this scheme in
more detail, including a recommendation on how to proceed.
14.
St Georges Field Crossing –
Feasibility work is complete and is currently being reviewed. The
next stage will be to either undertake a consultation or to seek a
decision on the next steps. There are dependencies upon the nearby
Castle Gateway scheme that strongly impact what action will be
taken.
15.
City Centre Bridges –
Feasibility work is complete and this report covers this scheme in
more detail, including a recommendation on how to proceed.
16.
People Streets at Ostman Road
– Feasibility work is complete and this report covers the
scheme in more detail, including a recommendation on how to
proceed.
17.
Hospital Fields Road Cycle
Improvements – The first outputs of the feasibility work have
been received, including outline design proposals. These are
currently being reviewed and evaluated. The intention is to
undertake a consultation when this work has been fully
completed.
18.
Fishergate Gyratory Scheme –
Sustrans have provided their proposals on how this route could
potentially be improved for Active Travel. This is currently being
reviewed and Officers are evaluating what further activity needs to
be completed prior to a consultation process on these
proposals.
19.
Wheldrake / Heslington Scheme
– Feasibility work has not been completed for this specific
route, however feasibility has been completed for a very similar
route with some overlap (Heslington / Elvington). Officers believe
the work that has been completed on this route includes sufficient
information to infer certain conclusions on the Wheldrake /
Heslington Scheme. This report covers these conclusions and
includes a recommendation on how to proceed.
20. Acomb Road Cycle Scheme – Feasibility work has not yet commenced as we continue to undertake a procurement process to obtain design and feasibility support. This process has taken longer than anticipated, partly due to granting extensions to potential bidders. The transport consultancy industry is under a resourcing pressure at present and granting extensions to the bidding process is sometimes necessary to ensure that we receive sufficient numbers of compliant and affordable bids.
Project Outlines
Background
21.
In March 2022 the Authority was
informed of the outcome of its most recent bid to the government
for Active Travel Fund support. The government approved £150k
of funding for Cycle Parking Improvements and £200k of funding
for People Streets schemes at Clifton Green Primary School and
Badger Hill Primary School.
22.
Further information on the content
of this bid can be found in Background Paper 2.
23. To ensure that these schemes are delivered in line with the expectations of both the Government and the Executive Member, a Project Outline is presented as part of this report. Once approved, officers will proceed with feasibility work in line with the agreed objectives and scope.
Options
24.
Option 1 – Approve the
proposed Project Outlines for the ‘City Centre Cycle Parking
Improvements’, ‘People Streets at Clifton Green Primary
School’ and ‘People Streets at Badger Hill Primary
School’, as per Annexes 1, 2 and 3.
Proceed to undertake feasibility work on each scheme to understand
costs, timescales, outline designs and consultation feedback to
inform a further decision prior to implementation.
25. Option 2 – Do not approve the proposed Project Outlines and undertake further work to refine the proposals in line with the government funding grant conditions.
Analysis
Option 1
26.
City Centre Cycle Parking –
This project outline describes a scheme to improve the provision,
availability and quality of cycle parking within the extended
footstreet area of the city centre.
27.
The scope of the scheme is defined
such that it meets both the authority’s commitments to the
government within the associated bid, and also CYC’s
strategic objectives in relation to promoting modal shift.
28. People Streets Schemes – The project outlines describe schemes to improve the walking and cycling routes around the vicinity of two primary schools. The proposals are similar to the scheme that has progressed through feasibility at Ostman Road and is presented within this report.
29.
It is noted that £200k is
available for both these new schemes, however recent feasibility
work has shown that ~£700k would be needed to implement a
similar scheme at Ostman Road.
30.
The intention is therefore to
progress these schemes through feasibility as far as is possible,
such that sufficient information can be presented for a decision on
the best way forward.
31. Officer resource is in place and ready to start feasibility work on these schemes commencing immediately after a decision is made. It is not currently proposed to assign these schemes a formal priority, however this can be undertaken if required.
Option 2
32.
Should the proposed outlines not be
approved, officers will take away feedback and attempt to revise
the proposals for reconsideration at a future session.
33.
Should the decision be to modify the
proposals to broaden or reduce the scope of works then officers
will assess the impact of these changes. Due to the fact that these
schemes are government funded, the Authority must ensure it
complies with the grant funding conditions which apply to this
work.
34. If proposed alterations can be incorporated without impacting grant funding conditions or introducing other such risks then this will be undertaken and the schemes will progress without coming back to a future session. Otherwise, a further report will be brought back to highlight these risks and propose a way forward.
Navigation Road TRO
Background
35.
The Executive Member for Transport
approved the implementation of an Experimental Traffic Regulation
Order (“ETRO”) in Navigation Road in June 2020 as part
of the implementation of the Navigation Road Cycle Scheme.
36. This report sets out the results of the consultation, alongside the assessment of the impacts of the ETRO with a view to making a decision about making the TRO permanent.
Consultation
37.
The consultation was available
between 2 May and 27 May 2022, open to all wanting to share their
views on the trial.
38.
The online questionnaire received
150 responses from residents and businesses. The responses received
can be found in Annex 7.
39.
Key points to summarise from the
consultation include:
a.
52% of respondents indicated that
the trial had a positive impact on movement on Navigation Road
whilst 42% of respondents stated that the trial had a negative
impact.
b.
11 responses received were from
local businesses. 27% of the businesses responded the trial had a
negative impact, with 45% stating a very negative impact on their
business. 18% of business reported a positive impact, and 9% stated
the trial had a very positive impact.
c.
The main reasons stated for opposing
the trial were: causes congestion / slow traffic, doesn’t
reduce traffic / forces it elsewhere, causes more air pollution due
to congestion, longer journey times, negative effect on surrounding
roads, need to drive further now / direct routes cut off.
d.
The main reasons stated for
supporting the trial were: reduced traffic, improved safety for
cyclists and better environment for pedestrians.
e.
The experience of cycling on
Navigation Road improved with the trial, 72% of responses of those
that cycle on Navigation Road, stated that they feel safer due to
the trial in place.
f.
The experience of walking on
Navigation Road improved with the trial, 48% of responses of those
that walk on Navigation Road stated that they feel safer due to the
trial in place.
g.
39% of motorists that responded
stated that the trial had a very significant impact on their car
use habits, with 10% stating car journeys have been reduced since
the trial. 33% stated their methods of travelling have altered due
to the trial.
Options
40.
Option 3 - Decide to make the Experimental Traffic
Regulation Order relating to Navigation Road cycle scheme
permanent.
41. Option 4 – Do not make the Traffic Regulation Order relating to Navigation Road cycle scheme permanent and begin work to understand what would be required to revert the site back to how it was pre-implementation.
Analysis
Option 3
42.
Traffic surveys were undertaken
before implementation (1 month) and post implementation (6 months)
The following information was captured:
a. Walmgate queue length comparison
b. Pedestrian flow comparisons
c. Cycle flow comparison
d.
Vehicle flow comparisons (excluding
cycles)
43.
It is clear from survey work that
the scheme has not had a dramatic effect on the local road network,
however there is a limit to what can be inferred from the data. It
is proposed that the scheme continues to be observed for a longer
period of time to ensure that the scheme impacts have not been
inaccurately monitored.
44.
It was noted that on Saturdays queue
lengths on Walmgate are generally slightly better or similar to the
baseline, on Sundays queues are in general slightly worse than
baseline, on Tuesdays queues are shorter than the baseline.
45.
Pedestrian flows have increased on
both parts of Navigation Road and significantly on the section
where the new one-way motorised vehicle restriction is in
place. These increases are seen throughout the week.
46.
Cycle flows initially dropped on
weekdays on both sections of Navigation Road but have now surpassed
the pre-implementation levels. Flows on Saturdays and Sundays have
not followed the same trend.
47.
Compliance with the restrictions is
generally good over the 12 hour survey periods. Delivery mopeds
have been observed using the contra-flow cycle lane, though
compliance is sufficient to suggest that additional enforcement is
not required.
48.
There are sufficient funds available
within the budget to make this TRO permanent and to undertake
further monitoring of the scheme.
49. The separate ‘Foss Islands Road / Navigation Road Local Safety Scheme’ is currently facing delays due staff resourcing issues, however that has no impact upon completion of this scheme.
Option 4
50.
If the Experimental Traffic
Regulation Order is not made permanent then it will expire in March
2023, at which point motor vehicles will again be permitted to
travel along Navigation Road in both directions. This is the
default outcome if no further action is taken.
51. Before this happened it would be necessary to undertake work to ensure that the highway layout is safe, including potential removal of the ‘wands’ and other measures that have reduced the width of the carriageway.
City Centre Bridges
Background
52.
The outline of this scheme was
approved by the Executive Member at the February ’22
Executive Member Decision Session (See Background Paper 3)
53.
The City Centre Bridges consist of
Ouse Bridge, Skeldergate Bridge and Lendal Bridge. These bridges
provide critical access through the city over the River Ouse for
pedestrians, non-motorised users (NMU’s) and motorised
vehicles users.
54.
The aims of the project are to
address safety and amenity issues for cyclists, specifically
focussing on reducing conflicts between cyclists and motor vehicles
relating to ‘close / unsafe overtaking’.
Consultation
55.
External consultation has not yet
occurred for this scheme. It is possible that undertaking a
consultation on these proposals will not be productive due to the
very minor nature of the works, covering only minimal signing and
lining. These proposals are proportionate to the limited £15k
budget.
56.
It is expected that should the
scheme go out to consultation that the bulk of the responses will
be to suggest that more ambitious alternative proposals are
explored and that the works are significantly expanded in
scope.
57. The recommendation is to proceed with a limited consultation prior to implementation, and to manage expectations on what can be achieved within the available budget.
Options
58.
Option 5 - Confirm that the proposals presented for the
City Centre Bridges scheme align with the approved Project Outline
and decide to proceed with consultation, detailed design and
implementation.
59. Option 6 – Do not approve the proposals.
Analysis
Option 5
60.
Refer to Annex 11 for the
Feasibility report relating to this scheme. The content of this
report will not be replicated here, however key points will be
highlighted and addressed to support a decision.
61.
Recommendations
include:
a.
Liaise with North Yorkshire Police
to carry out a driver education programme on the dangers of close
passes to cyclists.
b.
Apply to the Department for
Transport for Signs Authorisation to use the “Give Cyclists
Space” sign for all bridges. If authorisation is granted, then the
design of these signs will be taken forward and implemented.
c.
Design road
markings using cyclist symbols (Diag 1057) for Ouse Bridge and
Lendal Bridge. The Lendal Bridge road markings would be installed
following the maintenance and resurfacing works of the
bridge.
62.
North Yorkshire
Police have already created ‘Operation Close Pass’,
whereby plain clothed police officers collect evidence of unsafe
overtaking and take action. It is therefore proposed that officers
engage with NYP to offer assistance in potentially carrying out
this operation on or nearby the city centre bridges.
63.
The feasibility
report has identified a potentially suitable sign that can be used
to raise awareness and discourage close overtaking. Special
permission is required from the Department for Transport to use
this sign on the Highway. Work has commenced to seek this
permission. The recommendation is to complete this work and the
implement this signage on the bridges, as described within the
report.
64.
The feasibility
report also suggests the implementation of road markings to further
raise awareness and discourage close passing. It is recommended
that this is pursued in line with the attached report.
65.
Motor vehicles
closely overtaking cyclists is intimidating, potentially dangerous
and a contributing factor preventing people to consider using their
bike.
66.
Skeldergate Bridge, Ouse Bridge, and
Lendal Bridge all have narrow carriageways. In order to change to
the width of the carriageways or introduce segregated cycle
facilities, the existing pavements would need to be narrowed, or
extreme structural changes to the bridges would need to be
undertaken. This cannot be achieved within the £15k of this
scheme and therefore these solutions have been ruled out.
67.
Over the last five years, five
accidents have been reported that involved cyclists on the three
city centres bridges. Of these accidents, two were on Lendal
Bridge, two on Ouse Bridge, and one was on Skeldergate Bridge.
These accident data suggest that there is little difference in the
safety of the bridges for cyclists.
None of the accidents reported over the last five years involved a
car unsafely or closely overtaking a cyclist. This suggests that
close/unsafe overtakes are not a primary cause of accidents on the
three bridges of interest.
This does not undermine the purpose of the scheme however, as close
passing does still discourage cycling journeys even if it does not
appear to be reflected in injury accidents on the bridges.
68. Table 1. Figures for City Centre Bridges
Bridge |
Road Width (metres) |
Two-way vehicle Journeys (24hrs) |
Two-way Cyclist Journeys (24hrs) |
Vehicles that were Cyclists |
AM Cyclists (%) |
PM Cyclists (%) |
Skeldergate |
7.25 |
22,000 |
680 |
3% |
n/a |
n/a |
Ouse |
7 |
10,000 |
1,300 |
12.8% |
30.4% |
32.8% |
Lendal |
7 |
13,300 |
2400 |
18% |
26.5% |
25.5% |
69.
Local Transport Note LTN 1/20
outlines that roads with a two way daily traffic flow of over 6,000
vehicles should separate vehicles and cyclist traffic by, for
example, a fully kerbed cycle track, stepped cycle track or
on-carriageway light segregation. All of the above would likely
require assigning ~3m carriageway space to provision of these
facilities.
Each bridge has a carriageway cross section of 7.25m or less, so it
is not possible to develop new segregated facilities compliant with
LTN 1/20 without removing traffic lanes, removing pedestrian
footpaths, or reconstructing the bridges. It is for this reason
that an LTN 1/20 compliant solution has been found to be not
feasible.
70.
Skeldergate Bridge does have cycle lanes at
present, but these are below the current LTN 1/20 minimum width
guidelines of 1.5m as they are less than 1m wide. The bridge is the
widest of the three (7.25m), but the designer does not recommend to
implement 1.5m cycle lanes on the bridge given this would still
lead to substandard vehicle lane widths which would introduce its
own safety issues.
71.
The designer considered the use of double white
lines. These prohibit drivers from entering the carriageway used by
opposing traffic. In order to implement “No Overtaking”
restrictions on the city centre bridges, an approved Traffic
Regulation Order (TRO) would be required. However, these orders
were ruled out by the designer because they are not seen as
suitable or enforceable on these specific bridges. This is also the
case for “No Overtaking” signs. Therefore, the designer
did not recommend further investigation of these options
72.
Speed reduction from 30mph to 20mph
was considered, however the designer did not recommend that this is
a suitable solution for such a short section of road. This could be
an effective change as part of a wider 20mph zone within the city
centre, but would have to be explored separately.
73.
74. These proposals are affordable within the currently available budget.
Programme Budget Summary
Background
75.
Annex 5 contains an overall budget
summary for the programme covering original funding, spend in
previous years, and remaining budget. The recommendations contained
within this report make reference to the current budget assignment
for the programme and for individual projects.
76.
The February 2022 EMDS Active Travel
Programme report highlighted the issue that there is insufficient
budget within the programme to deliver every scheme.
77.
A decision was made to make
decisions on individual projects as and when sufficient information
becomes available to make this decision, without waiting for cost
estimates to be available for every project on the programme. This
is the approach that has been taken to date.
78.
This report expands on this approach
and lays out budget considerations relevant to the decisions
presented within this report.
Options
79.
Option 6 - Support the approach to managing the programme
budget laid out in this report. Note the programme budget summary
attached in Annex 5.
80. Option 7 – Do not support the proposed approach to managing the budget and attempt to work up an alternative approach.
Analysis
Option 6
81.
Please refer to the programme budget
summary attached as Annex 5.
82.
This summary shows that sufficient
funds are available to progress the recommendations presented for
Navigation Road and City Centre Bridges schemes. This funding is
provided from the Local Transport Plan government funding rather
than specific Active Travel Fund government funding.
83.
This summary shows that a total of
£1.127M of primarily government grant funding is shared across
6 schemes, many of which are very significant in ambition and
scope. This includes the A1237 Bridge Scheme, Wheldrake /
Heslington Path scheme, and the People Streets at Ostman Rd
schemes, which are presented for decision within this report.
84.
Of this sum, £128k has been
spent in previous years across all six schemes. This includes
commissioning of feasibility work and associated costs.
85.
This summary demonstrates that there
are insufficient funds within the programme to implement the
Wheldrake / Heslington scheme where high level cost estimates are
current in the range of ~£3M.
86.
To increase the chances of
delivering schemes on the ground, it is proposed to consolidate the
budget from schemes that are shown to not be feasible in practical
or budgetary terms. This is reflected within the recommendations
for each individual scheme.
87.
Due to the fact that a portion of
this funding is from the Active Travel grant, This approach
requires support from the Department for Transport, and this will
be sought through direct communication.
88.
Initial conversations have been
undertaken between officers and representatives of the DfT and
Active Travel England. No formal agreement has yet been reached,
however officers are confident that we can satisfy the requirements
of the funding body.
89.
The People Streets at Ostman Road
scheme is also part of this £1.227M budget, however it should
be noted that the government did not grant the Authority with
funding to specifically deliver this scheme. It is therefore
important that separate funding is sought to deliver this scheme so
that the government grant funding can be shown to have been spent
in line with the grant conditions.
A1237 Bridge Scheme
Background
90.
This scheme originated from a bid to
government for Active Travel Fund support. This partially
successful bid is attached as Background Paper 1.
91.
In February 2022, the Executive
Member for Transport approved the project outline attached in
Background Paper 5 for the scheme to convert the outline bid into a
defined piece of work.
92. Feasibility work has been completed and this report lays out the conclusion of that work, including recommendations to divert limited resources to other schemes within the programme and pursue a more limited piece of work through the Safety Scheme Review.
Options
93.
Option 7 - Agree to reassign resources to the wider
programme, subject to DfT support.
Consideration of comprehensive Active Travel Provision is to be
explored as part of the Outer Ring Road works.
Shorter term safety interventions to be considered as part of the
separate Safety Scheme Review.
94. Option 8 – Do not agree to reassign resources, and attempt to explore alternative ways to achieve significant Active Travel improvements.
Analysis
Option 7
95.
Feasibility work for this scheme has
been completed and is attached as Annex 10. The content of the
report will not be replicated here, but key points will be
highlighted and addressed to support a decision.
96.
The primary conclusion of this work
is that the scheme is not viable and the objectives cannot be
achieved within the currently approved scope.
97.
The key reason that the scheme is
not feasible relates to practical engineering considerations of
implementing civil construction works on the bridge. The
feasibility report finds:
“The bridge decks
preclude the construction of any intrusive works including a
stepped or segregated cycle track as this would impact on the
integrity of the bridge structure and the side-inlet drainage
provision. This along with the constrained width severely restricts
the options available within the current highway corridor. It is
therefore not considered feasible to produce an active travel
scheme within the existing corridor that provides a safe, smooth,
and attractive facility for pedestrians and cyclists
[…]”
98.
Rather than simply return the
remaining funding to the government it is proposed that officers
attempt to obtain support from the DfT to keep the funding within
the programme, to increase the chances of successful delivery of
the remaining schemes.
99. There are currently plans for the Outer Ring Road project to extend to this area of the ring road. Whilst it is not possible to make any decisions at this point on the detail of the Outer Ring Road scheme at this location, it can be stated that any such scheme would appropriately consider active travel provision as part of its proposals. This is seen as the most likely viable route to substantially improving active travel provision at this location.
Option 8
100.This option rejects the proposal to reassign
resources and represents the decision to pursue alternative means
to achieve the current objectives of this scheme, prior to any work
on the Outer Ring Road scheme.
101.There are currently no identified potential
routes to achieve this, and this option is therefore not
recommended.
102.The feasibility report attached as Annex 10 does
suggest pursuing a potential new bridge over the river and rail
line to provide a dedicated active travel facility. This is not
supported or recommended for a number of reasons.
103.Undertaking work to explore the creation of a
new bridge would present new risks to the existing Outer Ring Road
project in terms of any potential Compulsory Purchase processes and
is therefore not supported.
104.Without undertaking any feasibility on a new
bridge it can be safely assumed that costs would be in the
multi-million pound range. This is clearly outside of the budget of
the current programme.
105.Pursuing more limited safety improvements is
already proposed as part of Option 7.
Wheldrake / Heslington Scheme
Background
106.There has been an ambition to provide a high
quality active travel corridor between the villages of Wheldrake
and Heslington for many years. Previous studies have explored
potential options for implementation, but have generally identified
significant challenges relating to costs and land ownership
issues.
107.City of York Council received grant funding to
explore this scheme once again in the ‘Emergency Active
Travel Fund Trache 2’ round of bidding, see Background Paper
1.
108.In February 2022 the Executive Member approved
the outline of this piece of work, which can be found in Background
Paper 4.
109.In parallel, CYC have been working with Sustrans
to undertake a similar piece of feasibility on a route between
Heslington and Elvington. This piece of work has recently concluded
and provides a lot of information that is relevant to this
scheme.
110.This report lays out the conclusions that have been reached based on this report and other work completed to date.
Options
111.Option 9 - Agree to reassign resources to the wider
programme, subject to DfT support.
Pursue the existing feasibility work instead via the forthcoming
LCWIP.
Continue to engage with upcoming developments in the local area to
ensure that active travel provision is considered
appropriately.
112.Option 10 – Undertake further feasibility work now, with a view to progressing the scheme as far as possible.
Analysis
Option 9
113.Sustrans have undertaken a feasibility study
covering a potential active travel route between Heslington and
Elvington (not Wheldrake), refer to Annex 9. The content of the
report will not be replicated here, however key points will be
highlighted and addressed to support a decision.
114.This feasibility report does cover a significant
section of route that is relevant to the Heslington / Wheldrake
route and some reasonable assumptions can be made based on this
report.
115.This report gives a high level cost estimate in
the order of £4M for provisions of a route between Heslington
and Elvington.
116.Whilst costs would clearly not be the same for a
route between Heslington and Wheldrake, it is reasonable to assume
that costs would be in the same order of magnitude, especially as a
significant part of the route is the same.
117.Based on these estimates, there is insufficient
budget within the programme to deliver this scheme. Even if all
other schemes within the programme were closed down and their
funding diverted to this scheme there would still be insufficient
budget to implement a scheme on the ground.
118.Initial conversations have been undertaken with
relevant landowners on the routes to understand the land ownership
implications. The detail of these conversations cannot be reported
publicly due to data protection considerations, however land
ownership issues do continue to be a secondary significant barrier
to scheme feasibility.
119.It is recommended that officers attempt to
obtain support from the DfT to keep the funding within the
programme and re-assign it to other schemes to increase the chances
of successful delivery of the remaining schemes.
120.Further work on this scheme is proposed to be
undertaken via the forthcoming LCWIP.
121.It should also be noted that opportunities exist to achieve potential benefits through upcoming large scale developments in the local area, including consideration of active travel provision. This will be pursued as part of this option.
Option 10
122.This option involves pursuing the scheme further
and commissioning a detailed piece of feasibility work on this
specific route.
123.A cost estimate has been obtained through an
expression of interest process and this is estimated to cost
approximately £265k.
124.This is not seen to be a cost effective use of the funds and is therefore not recommended.
People Streets at Ostman Road
Background
125.High volumes of traffic along Ostman Road at
peak school pick-up and drop-off times, especially outside Carr
Infants and Junior schools, has been identified as an issue that
impacts the safety of children and parents as they make their way
to school. There is also a desire to encourage modal shift away
from motor vehicles onto more sustainable modes of transport.
126.In 2020, Sustrans carried out a one day trial in
which temporary build-outs were placed outside Carr Junior school
during peak times to discourage parents from parking outside
schools and make the roads safer for children. The trial was
popular amongst parents and residents interviewed.
127.A successful grant funding bid was made to the
Department for Transport to take this further, with the bid text
stating:
“After a successful trial of a people street concept at Carr
Junior School in association with Sustrans last year we are
including changes to Ostman Road in Acomb as a pilot scheme in this
application for potential future rollout across the city” ,
refer to Background Paper 1.
128.In the February 2022 Executive Member Decision
Session, the Executive Member for Transport approved the Project
Outline for this scheme (Background Paper 6), turning the broad bid
text into a firm scheme for officers to progress.
129.Feasibility work has now been completed and a
summary report can be found in Annex 8.
130.This report concludes that none of the proposed options are affordable within current budgets, however the recommendation is to seek additional grant funding at the next round of Active Travel funding to allow the scheme to progress to delivery.
Consultation
131.An electronic consultation has been carried out
with local ward councillors for Acomb and external stakeholders.
Targeted external stakeholders included residents and businesses on
and in the immediate vicinity of Ostman Road, and parents and staff
affiliated with Carr Infant and Junior Schools.
132.Refer to Annex 7 for a summary of the consultation responses received.
133.The majority of respondents (53%) used the
street to drop off and collect children from school. Cars were the
most prevalent mode of transport used by respondents (43%), with
walking the second most common mode (39%) and cycling third
(12%).
134.Asked about the conditions for pedestrians and
cyclists, the responses indicated that the current provision is not
good. Most respondents agreed that action needed to be taken to
improve pedestrian safety and amenity on Ostman Road.
135.The purpose of this scheme is to encourage
people to walk and cycle to school by improving conditions. 40% of
respondents said they would walk / cycle instead of driving if
conditions improved. 36% of respondents were undecided on this
question, and 25% of respondents indicated they would not change
modes even if conditions were improved.
136.This feedback suggests that there is a real
possibility of influencing people’s behaviour and that there
is a level of support for interventions to re-prioritise the
roadspace. There were however several concerns relating to how that
would be achieved.
137.In terms of potential changes to restrictions
there was no single option that gained majority support, with a
restriction on peak time parking being the most popular (47%). 24%
of respondents did not support any form of additional parking
restrictions.
Other pieces of key feedback included:
138.There were several doubts that parking
restrictions would be enforced, with concerns raised that those
restrictions that are currently present are not effectively
enforced. This is a valid concern that will be investigated in more
detail at the next stage of the scheme, however officers are
confident that an effective enforcement arrangement can be
implemented.
139.A common piece of feedback was that parking
restrictions would move traffic and parking to neighbouring
streets. This is likely correct; based on the consultation feedback
officers believe a certain portion of motorists would still drive
even if conditions were improved for pedestrians and cyclists. This
should be seen as one of the primary downsides of this scheme and
officers are not able to offer a complete mitigation to this issue.
As with all parking restrictions in the city, there would be an
unavoidable level of traffic redistribution.
140.On this point, a common piece of feedback was
that a number of respondents indicated that they had no alternative
to driving, whether due to their work schedule or other related
practicalities. This is understood and it should be understood that
this scheme will significantly disbenefit some motorists.
141.Several consultees responded with specific
feedback relating to their disability. It should be noted that
there were a significant number of these responses that are not
included within the attached annex due to the fact that they
contained personal data. These responses will be given special
consideration here.
142.This feedback generally indicated that they didn’t feel they would be able to access the school at all if restrictions on parking were introduced, either due to mobility related disabilities or due to the specific disabilities of their children, for example learning disabilities. The impact on these users is different to the impact on general motorists and is potentially much more significant.
143.It is therefore proposed that when the parking restrictions are turned into a formal Traffic Regulation Order that exemptions are considered to ensure that users with disabilities appropriately considered. The feedback from this consultation process has been especially helpful in this regard and further more targeted consultation and assessment of any impacts on this issue will be undertaken prior to implementation.
144.Another common point raised by residents of Ostman Road and neighbouring streets was a feeling that they should have some form of priority or special consideration on the street by merit of being a resident. The primary purpose that this is usually achieved is by means of a residents parking scheme, however this is not being proposed in this case.
145.There were several responses that suggested removal or diversion of bus services would improve the situation because buses often get caught up in the traffic and contribute to the congestion.
146.It is accepted that buses do get caught up in traffic and block the street on occasion, however officers do not support the idea of solving this issue by restricting bus access. Public Transport is senior to car borne commuting on the Council’s Road User Hierarchy, and therefore it is proposed that a more strategically consistent approach is to restrict the motor vehicle side of the issue rather than the buses.
Options
147.Option 11 - Note the outcome of the feasibility
work for the ‘People Streets at Ostman Road’ scheme
laid out in this report, and decide to seek further funding before
proceeding to implementation.
Seek Active Travel grant funding support at the next round of
bidding.
Progress with detailed design work on ‘Design Option 1’
described in the attach Feasibility report, in advance of receiving
additional funding.
Analysis
Option 11
148.The attached Feasibility report (Annex 8)
explores 3 preliminary design options that each achieve the
objectives of the scheme, but have slightly differing features and
cost estimates.
149.Cost Estimates Table – People Streets @ Ostman Road
|
Design 1 |
Design 2 |
Design 3 |
Feasibililty work (already incurred) |
£35,974 |
£35,974 |
£35,974 |
Further design and development |
£58,794 |
£64,873 |
£83,308 |
Construction |
£419,959 |
£463,380 |
£595,055 |
Risk margin |
£191,501 |
£211,302 |
£271,345 |
|
|
|
|
Total |
£706,228 |
£775,529 |
£985,682 |
150.As per the programme budget summary (Annex 5),
there are insufficient funds within the budget to deliver any of
the proposals. It is therefore recommended that additional funding
from the next round of government Active Travel grants is sought
prior to implementation.
151.Such a bid would be more likely to be successful
if CYC could present a ‘shelf-ready’ scheme with most
of the work complete, instead of a broad outline of intentions. The
work that has already been completed goes a long way to achieving
this, however progressing a specific design proposal to the
detailed design stage would go even further to achieving this
aim.
152.Officers are recommending that Design Option 1
within the attached report is progressed to detailed design
immediately following this decision session. This option achieves
the objectives of the project and is the cheapest of the proposals,
which will go some way to improving the chances of receiving
additional funding.
153.The traffic regulation order that is proposed to
be included within the detailed design is a peak-time no-parking
zone. This is the restriction that received the most support in the
consultation process (see Section 7) and officers are confident
that it can be implemented in a way that will achieve the
objectives of the scheme.
154.Trialling a traffic restriction prior to any
built environment changes is not being offered as an option. Advice
from the Principal Designer indicates that the built environment
changes are an essential part of the scheme in terms of achieving
the objectives, and a trial without the physical changes would not
be successful, nor would it provide any valuable learning.
155.Recorded personal injury accident data shows
there was one incident in this location, ‘slight’ in
severity, recorded between 01/01/2017 and 31/12/2021. The incident
occurred between a moving vehicle and a parked car. This does not
represent a significant trend that can be directly addressed,
however design proposals were still created with safety as a
priority consideration. Also, despite there not being a significant
safety issue recorded on the street, the objectives of encouraging
modal shift remain pertinent.
156.Replication of the 2021 Sustrans trial design
layout was considered however it was found that this layout could
not be implemented permanently to a high standard due to the fact
that the carriageway is constructed of jointed concrete, therefore
making such a solution extremely cost-prohibitive.
157.The recommended design solution includes the
following features:
Gateway markings to indicate a changed priority space and to make
restrictions more visible.
Introduction of a peak-time parking restriction between gateway
features.
Replacement of concrete footway with improved surface to allow
implementation of a shared space facility.
Planting features, benches and public realm improvements to make
the route more desirable for active travel users, to encourage
modal shift.
Installation of 2 new parallel pedestrian and cycle
crossings.
Installation of benches and planting to improve public realm,
therefore encouraging modal shift.
Renewal of existing road cushions and speed tables.
158.Implementation of the proposed changes requires
the removal of a number of trees. It is proposed to replace these
trees, and in greater number.
159.Existing
conditions and all design proposals scored Amber on the LTN 1/20
Junction Assessment Tool (JAT). This is due to the only significant
junction change being the continuous footway. However, due to the
quiet nature of the street, the proposed facilities are considered
appropriate.
160.Due to the fact that this scheme is intended to
be funded through a government grant, the requirements of LTN 1/20
are especially relevant. Officers are confident that the proposed
solution does offer a significant improvement, and that the
reasoning provided to Active Travel England via the bid process
will be sufficient to address this issue.
161.Existing conditions on Ostman Road scored below
the 70% pass threshold at 66% on the LTN 1/20 Cycling Level of
Service (CLoS) assessment. Design 1 would increase this score to a
pass score of approximately 76%.
162.Surveys carried out on Ostman Road revealed that
the majority of pedestrians cross near to the school entrances
where there is currently a high occurrence of illegal parking. The
TRO restricting parking within the gateway features will reduce the
number of parked vehicles, clearing the road and making it safer
and easier for pedestrians to cross.
163.Parallel crossings will make it safer and easier
for pedestrians to cross the road, as they will be given
priority.
164.The enhanced buffer will further separate
children from the road, making it easier for parents to safely walk
or cycle them to school.
165.Traffic flows along Ostman Road are considered
low, meaning that cyclists can use it as an on-street quiet route
in line with LTN 1/20 standards. The widened shared footway on the
north and south sides of the road also offer space for children to
cycle safely beside their parents.
Option 12
166.This option still proposes to seek additional
funding to implement one of the three preliminary design solutions,
however involves undertaking further work to determine which option
should be taken forward to detailed design.
167.It is thought that stakeholders may want to offer additional input on the detail of the proposals and that a further consultation could enable this.
168.This can be undertaken, however timescales mean that it is unlikely a ‘shelf-ready’ bid could be proposed to the government if this stage is added to the process, thus reducing the likelihood of receiving grant funding.
Council Plan
169. “Getting Around Sustainably” is one of the key objectives of the Council Plan. The Active Travel Programme directly influences the outcome of this objective by pursuing tangible built environment improvements that strongly influence the way in which people travel around the city.
· Financial
The Active Travel programme is funded from a combination of grant funding and council resources allocated through the capital programme. The recommended options within the report maintain the programme within the available budget. This is in line with the previous decision to prioritise schemes once costs were known for individual schemes. Where schemes cannot be delivered DfT confirmation will be needed before the grant funding can be reallocated.
·
Human Resources
(HR)
There are no HR
implications
·
Equalities
Refer to the attached Equalities Impact Assessment (Annex 12)
·
Legal
It is the duty of a local
authority to manage their road network with a view to achieving, so
far as may be reasonably practicable having regard to their other
obligations, policies and objectives, the following
objectives:
(a) securing the expeditious movement of traffic on the authority’s road network; and
(b) facilitating the expeditious movement of traffic on road networks for which another authority is the traffic authority.
Local authorities have a duty to take account of the needs of all road users, take action to minimise, prevent or deal with congestion problems, and consider the implications of decisions for both their network and those of others.
If the decision is made to give
permanent effect to the temporary traffic order in this report, the
decision maker should consider the criteria contained within
section 122 of the Road Traffic Regulation Act 1984 and in
particular the duty to make decisions to secure the expeditious,
convenient and safe movement of vehicular and other traffic
(including pedestrians).
·
Crime and
Disorder
There are
no Crime and Disorder implications
·
Information Technology
(IT)
There are no
IT implications
·
Property
There are no Property implications
· Other
Highway implications are addressed in the body of this report.
Risk Management
170. Every project within the Active Travel Programme is managed in line with the Corporate Risk Management Strategy. This involves action by assigned Project Managers to identify, manage, and mitigate specific risks to delivery.
Contact Details
Author: |
Chief Officer Responsible for the report: |
|||||||
Christian WoodSmart Transport Programme ManagerTransport01904 551 652
Shoaib Mahmood Transport Project Manager Transport
James Williams Transport Project Manager Transport
Nigel Ibbotson Transport Project Manager Transport
Beth Old Transport Project Manager Transport
Richard Milligan Transport Project Manager Transport
|
James GilchristDirector of Transport, Environment and Planning
|
|||||||
Report Approved |
√ |
Date |
08/07/2022 |
|||||
|
||||||||
|
|
|
|
|||||
Specialist Implications Officer(s) List information for all
Financial: Legal: Jayne Close Heidi Lehane Finance Legal 01904 554
175
01940 555 859 |
||||||||
Wards Affected: [List wards or tick box to indicate all] |
All |
Y |
|
|||||
|
|
|||||||
For further information please contact the author of the report |
|
|||||||
Background Papers:
Background Paper 1 - EATF Tranche 2 Application
Background Paper 2 - ATF Tranche 3 Bid August 2021
Background Paper 3 - Project Outline – City Centre Bridges v2.0
Background Paper 4 - Project Outline – Wheldrake to Heslington v1.0
Background Paper 5 - Project Outline – A1237 Scheme v1.0
Background Paper 6 - Project Outline – People Streets at Ostman Road
Annex 1 – Project Outline – City
Centre Cycle Parking
Annex 2 – People Streets at Clifton Green PS
Annex 3 – People Streets at Badger Hill PS
Annex 4 - Active Travel Programme v6
Annex 5 - Active Travel Programme Budget Summary Jul-22
Annex 6 – Consultation Summary - Navigation Road v1.0
Annex 7 – Consultation Summary – People Streets at Ostman Road
Annex 8 – Feasibility Report – People Streets at Ostman Road
Annex 9 – Feasibility Report – Heslington to Elvington
Annex 10 – Feasibility Report – A1237 Bridge Scheme
Annex 11 – Feasibility Report - City Centre Bridges v3.0a
Annex 12 – Equalities Impact Assessment – People Streets at Ostman Road
Annex 13 – Equalities Impact Assessment – Navigation Road
List of Abbreviations Used in this Report
CYC – City of York Council
DfT – Department for Transport
ATE – Active Travel England
LTN 1/20 – Local Transport Note 1/20
ETRO – Experimental Traffic Regulation Order
TRO – Traffic Regulation Order
LCWIP – Local Cycling and Walking Infrastructure Plan
NYP – North Yorkshire Police